Nebius borrowed 3.5 billion dollars for data centres — and has to repay within a year
On Thursday the AI company Nebius raised 3.5 billion dollars from the American bank Citi. The money is to build data centres and buy graphics cards, the company says. The loan must be repaid in 364 days.
That last sentence is the most striking detail in the deal. A data centre of concrete, cooling and power supply stands for decades; even the graphics cards are counted in years. The financing lasts less than one.
Nebius Group N.V. is headquartered in Amsterdam and listed on Nasdaq in New York. It rents out computing power for other companies' AI work, and it puts its own European footprint at sites in Finland, France, the United Kingdom, Spain, Estonia and Iceland. That makes Nebius one of the larger European players in a market otherwise dominated by American providers — with the same caveat that applies to the Nasdaq-listed IREN in Badajoz: a head office does not settle where the ownership and the capital live.
The money is getting more expensive
Citi acts as arranger and security agent. The loan ranks ahead of the company's other debt and is backed by collateral, and the interest is, in the company's own words, "Term SOFR plus 2.75% per annum, increasing up to a maximum of 3.50% per annum". SOFR is the American benchmark rate the loan is priced on top of.
The price has risen. In July, Nebius took its first borrowing secured against assets: 775 million dollars at SOFR plus 2.50 percent, backed by deployed equipment and by the payments from a single customer the company describes only as being of high credit quality. August brought 5.75 billion dollars in convertible notes — debt that can be swapped for shares — split into 3.45 billion dollars at 0.50 percent due 2030 and 2.3 billion at 4.50 percent due 2034. The company's own half-year accounts put net cash from financing in the first six months at 9.16 billion dollars.
Four rounds in four months, each at a higher price or a shorter horizon. Chief operating officer Ophir Nave calls it a plan himself: "Sequencing our financing is how we optimize our long-term cost of capital."
A number that does not belong to the deal
In the same quote, Nave mentions "customer commitments of more than $40 billion of long-term contracts". The figure is worth reading closely. It is the company's own, no customers are named, and it is not the collateral behind the Citi loan — Nave offers it as the basis for financing Nebius expects to raise later. The company says it expects to end 2026 with 5 gigawatts of contracted power and, from 2027, to bring more than 1 gigawatt into service each year. Those figures, too, are the company's own.
It is worth holding all that alongside what happened in the same market ten days earlier, when Microsoft withdrew as the sole customer at Nscale's data centre in Loughton and the share price fell to roughly half. Contracted power and signed commitments are not the same thing as facilities that run and customers that pay.
Nebius has raised the money. What it bought will become clear when the loan comes up for renewal — in October 2027.
Sources
- Nebius's own announcement of 22 October — the 3.5 billion dollars, that the facility is senior and secured, Citi's role as arranger and security agent, the 364-day maturity, the interest wording, what the money is for, the quotes from Ophir Nave and the 40 billion dollars in customer commitments
- Nebius's second-quarter 2026 results — the July loan of 775 million dollars at SOFR plus 2.50 percent secured on deployed equipment and on payments from one customer, the 9.16 billion dollars of net financing in the first half, the 5 gigawatts of contracted power by the end of 2026 and the plan for more than 1 gigawatt a year from 2027
- Nebius's announcement of 24 August — that the convertible notes closed at 5.75 billion dollars in total, split into 3.45 billion at 0.50 percent due 2030 and 2.3 billion at 4.50 percent due 2034
- Nebius's announcement of 21 October — the company's own account of its European footprint: Finland, France, the United Kingdom, Spain, Estonia and Iceland