Italy's data centres asked for 100 gigawatts. Construction has started on 230 megawatts.
Italy's data centre industry laid out its arithmetic in Rome this week: nearly 37 billion euros of investment through 2036, if every approved project is built out. Some 26,000 full-time jobs — 11,900 direct, 11,000 indirect and 3,000 induced. Commercial capacity growing from 460 megawatts in 2025 to 2-2.3 gigawatts by 2031.
The figures come from the Italian Datacenter Association (IDA), the trade body for builders and operators, which presented its market study at its own Data Center Symposium. They sit alongside another number that tells a more awkward story.
100 gigawatts requested, 1.9 gigawatts of projects
Companies have asked the Italian grid for connections totalling between 60 and more than 100 gigawatts. That is 30 to 50 times the roughly 1.9 gigawatts that has made it as far as approval. Of that, 230 megawatts is under construction, 673 megawatts in development and 936 megawatts at a preliminary stage.
The gap is not a bottleneck. It reflects the fact that much of the queue consists of requests that will never become anything. Developers apply for grid capacity in several places to keep their options open, and the grid operator has to plan around demand that is partly invented for the occasion.
The industry's own delivery record points the same way. Between 2023 and 2025 the sector spent 7.1 of a planned 10.5 billion euros — 68 per cent. At that rate, the 37 billion becomes about 25. IDA itself forecast only 21.8 billion over five years and 2 gigawatts by 2031 as recently as October 2025, so the projection has been revised sharply upward in a year.
"The obstacles are primarily regulatory"
IDA president Luca Beltramino assigned responsibility plainly. "The obstacles are primarily regulatory in nature," he said, calling for national data centre legislation.
Enterprise Minister Adolfo Urso arrived with figures of his own: more than 7 billion euros already invested, and a further 25 billion announced. Those are not the association's ten-year projections, and they do not measure the same thing.
The report's own respondents, meanwhile, named something other than law as the threat that could halt the build-out: a shortage of specialised technical staff. Power, grid connections, water and cooling follow. Eighty per cent of project land sits on already urbanised or brownfield sites, which limits new land consumption but not energy consumption.
Regulation is not always the problem
It is worth holding the two stories side by side. In Italy the industry says regulation stands in the way of a build-out it has itself delivered only two thirds of. In Finland, Google's construction was halted because the environmental assessment was never carried out — there the regulator arrived too late.
Both cases come down to the same thing: a build-out moving faster than any authority can track, and therefore hard to plan around. A grid cannot be sized for 100 gigawatts when 98 of them are hypothetical.
Sources
- Il Sole 24 Ore — the IDA report's figures for investment, capacity, employment and land use, plus quotes from Luca Beltramino and ministers Urso and Pichetto Fratin
- The Next Web — the 60-100+ gigawatt connection requests, the 1.9 gigawatts of advanced projects, the 68 per cent realisation rate and IDA's earlier forecast (based on Bloomberg's account)
- Crypto Briefing — an independent account of the same IDA figures, including what a 68 per cent realisation rate would mean